Eyes Cross-Environment Testing

The Eyes cross-environment testing feature allows you to test your application on multiple platforms using a single, common baseline. This article explains how to do this in practice.

Overview

The Baseline Signature

The visual testing baseline consists of a set of images that are used as a basis for comparison of images captured during a test. A particular baseline is distinguished from other baselines by two types of information:

When a specific test is run on multiple platforms, all platforms will have the same baseline name, but by default, the environment will be specific for each platform since the precise look and feel of an application can potentially vary depending on the operating system, browser type, and viewport size. As a result, there is a separate baseline for each environment tested.

Cross-environment testing provides you with a way to use a single baseline for verifying multiple environments. While having to manage fewer baselines can be convenient, using a single baseline for multiple environments can potentially reduce the accuracy of the test because the matching algorithm needs to allow for valid differences between the environments.

The Environment Name

Eyes provides a way to assign a name to a specific environment. For example, we can give the name "desktop browser" to the environment composed of the Chrome browser, running on Windows 10, using a viewport size of 1500 x 960 pixels.

Eyes provides an SDK command that allows you to specify that a test should use a baseline that matches a specific named environment, instead of the baseline that matches the test environment. This is the basis for cross-environment tests since it allows you to specify, for example, that for a given test, the baseline that matches the "desktop browser" environment should be used for verifying all test runs irrespective of the OS, browser, or viewport.

Running Cross-Environment Tests in Practice

Visual testing using the cross-environment scenario consists of the following steps:

  1. Planning
  2. Setting up the test in the SDK and Test Manager
  3. Reviewing and resolving mismatches

Each of these steps is expanded on in the following sections.

Planning

The first step is to decide which environment will be the "master" environment. The choice of environment is dependent on many factors, such as your user base, your toolset, and more. Eyes does not have any specific preference as to which environment is used as a master. Let us assume that you have selected "desktop browser" as the master environment (Windows 10, Chrome, and a viewport size of 1500 x 960).

Setting Up the Test

Below are the basic steps you need to follow when setting up a test to run in a cross-environment scenario:

  1. First, you need to create a baseline for the master environment, referred to as the master baseline. If you have an existing baseline that is suitable, then you can use that and you don't need to run a special test.

  2. Next, you need to give a name to the environment used by the baseline. One way of doing this is in the Test Manager Environment page: Find the row with the OS, Browser, and viewport of the master baseline. In the 4th column (with the header "Name"), type in the name of your environment. If the name you add is already being used for a different environment, you will get a warning and you can either cancel or change the environment that the name refers to.

  3. Change your test so that it will run against the master baseline by configuring the SDK using the methods below:

Eyes eyes = new Eyes();
eyes.setBaselineEnvName("desktop browser");
// now call open...
  1. In most cases, since there are substantial visual differences between platforms, use a matching level of "Layout".
import com.applitools.eyes.MatchLevel;
// ...
eyes.setMatchLevel(MatchLevel.LAYOUT);
  1. When the test runs in the same environment as the master baseline, it is recommended that you use the Strict match level to detect visual regressions that are ignored in the Layout match level.

Reviewing and Resolving Mismatches

After a test runs, if there are any mismatches, you will typically want to review them and decide what action to take. In a cross-environment test, you work using all the usual Test Manager features. The only difference is that when the test environment is different from the baseline environment, you will not be able to update steps in the baseline or define regions such as ignore or match level. These operations must be done on a test that ran in the same environment as the baseline so that all the images in the baseline, and operations those images, are from the same environment.